After authorizing $370 billion in new funding for new, cleaner energy sources, Congress is turning to permitting reform: All the money in the world will not help if projects don’t have permission to build. Wednesday evening, Senator Manchin released proposed text for his permitting bill, which he apparently negotiated in return for his vote to authorize the energy funding. Unfortunately, the bill is not well-designed to speed up construction of new energy sources. But with a few strategic additions it could go a long way toward speeding up permitting to secure a cleaner, more reliable, and affordable energy future for the United States.
The biggest roadblock to energy sources is not financial; it is receiving permission to build. And many of the projects that we most need for a clean energy transition face particular permitting difficulties because they need permits from multiple states or local communities and the federal government. Our traditional energy commodities, oil and coal, are less dependent on building long-distance infrastructure because they can rely on existing railroads and pipelines, and they are easier to ship by multiple pathways using rail, road, and water transport. By contrast, cleaner energy products such as renewable electricity, natural gas, and hydrogen can only be shipped by new long-distance infrastructure.
Think of a long-distance power-line designed to bring renewable energy to market, a pipeline shipping natural gas to communities hoping to move away from coal, or a hydrogen pipeline designed to help replace fossil fuels. These linear infrastructure projects often need approvals from each state they cross and may also need approval from the federal government as well whenever they cross federal lands, borders, or streams.
There are two huge legal permitting challenges for these new cleaner energy projects.
So if we want to clean up our energy system and address the global energy crisis, which is causing energy shortages and price spikes around the globe, we need to speed up permitting. If the $370 billion authorized by Congress just goes to the few projects that would already have passed the permitting gauntlet, it will be money wasted. So we’ve seen a growing chorus of voices demanding reform to the permitting process to ensure this money isn’t squandered and that we can build a cleaner energy future.
The federal and state permitting challenges are linked because perhaps the most common proposal to speed permitting is to replace state and local siting processes with federal processes. For example, in 2005, the U.S. Congress gave the federal Department of Energy the power to designate areas that particularly needed more electricity transmission and gave the Federal Energy Regulatory Commission power to, in some circumstances, permit power-lines that hadn’t been approved by the states in those areas. Senator Manchin’s bill leans heavily on this method of speeding permitting: it gives federal government more power over permitting new power-lines and hydrogen pipelines.
The problem is that this is not an improvement at all when federally-approved projects are facing Kafkaesque challenges when they seek approval to actually build their projects. The energy sector where federal permitting is most common is in interstate natural gas permitting and these projects are routinely stopped by local objections even when they have federal approval. In fact, the two highest-profile recent gas pipeline projects—the Atlantic Coast Pipeline and the PennEast Pipeline—eventually had to give up on building their projects after years of expense and struggle, even though the federal government repeatedly backed both pipelines and both pipelines won blockbuster decisions in the U.S. Supreme Court.
If the Manchin bill passes as is, the gas pipeline industry can welcome the power-line and hydrogen industries to national regulation with this unwelcome news: “Even if the federal government backs you on every permit, and even if the Supreme Court backs you in every decision, no matter how long you wait, or how much you spend, states and lower courts will make life so difficult that your proposed project will never be built.”
The dysfunctions of federal permitting under court review are well known in energy policy. Congress’s 2005 grant of power to the Department of Energy and the Federal Energy Regulatory Commission was eviscerated by two federal appeals court decisions over the next six years. This is why the single project that really will be helped by the current Manchin proposal is the Mountain Valley Pipeline. The bill makes special provision for this project, directing that all actions “necessary for the construction and initial operation at full capacity of the Mountain Valley Pipeline shall not be subject to judicial review.”
The Manchin bill does almost nothing to help other energy projects stop endless court demands for further environmental review. The bill does address some less important timing issues so it’s important to keep straight three kinds of time limits:
- Time limit for the federal government to complete environmental review. The proposal directs a two year limit for environmental review of major projects and a one year limit for minor projects. Unfortunately, such deadlines are unenforceable—the federal government routinely misses even the statutory deadlines it is trying to meet. The deadlines may even be counterproductive if they encourage courts to stop projects and order further reviews because of concern that review was rushed to meet an artificial deadline.
- Time limit for plaintiffs to challenge a project after it receives its permit. This kind of “statute of limitations” is not harmful but of very little use. Smart plaintiffs hoping to stop infrastructure generally sue at the earliest opportunity because the best chance to stop an infrastructure project is before construction begins. So big projects are almost never held up by plaintiffs that waited years after the project was approved to bring their lawsuit.
- Time limit for courts to order more review on projects that have already been under review for years. Unfortunately, the Manchin proposal does not put any time limits on courts’ ability to hold up nationally-approved projects other than the Mountain Valley Pipeline. The federal environmental review law, the National Environmental Policy Act (NEPA), is a procedural statute simply intended to ensure the government did sufficient environmental review of a project. If the federal government has been reviewing the environmental consequences of a project for years and has approved it, and the court would still like more review, the court can order the government to do more review. But it is not reasonable to make a nationally-approved project, and all the consumers and producers that depend upon it, wait for the court and government to reach agreement on how much environmental review is enough.
The crucial importance of a time limit on judicial delay of projects is well explained in the Institute for Progress’s excellent recent report on “How to Stop Environmental Review from Harming the Environment“:
The time limit that would likely have a major impact on outcomes is restricting the ability of the courts to issue injunctions against projects that have undergone extensive environmental review under NEPA. This change would provide developers the certainty they need to invest in large-scale build outs of solar, wind, transmission and other clean energy infrastructure. Without a time limit on judicial injunctions, developers have a sword of Damocles perpetually hanging over their head, threatening the entirety of the project.
As it stands, the Manchin permitting proposal would be a serious lost opportunity that would be unlikely to significantly speed up construction of new energy projects. The focus on federalizing review of clean energy projects is particularly unhelpful when the proposal doesn’t address the problems that are making federal review the bane of energy project developers.
The good news is that the Manchin proposal could be improved relatively simply if it added limits on federal court and state delays on federal projects. Speeding up permits for nationally-approved projects would accelerate construction of all the new energy projects that it designates for federal review.